Hydrometallurgy plant and Danjiangwu Phase II wastewater treatment station control system
Apr 2025 — Sep 2025
Background
Hydrometallurgy automation project: centralized Siemens PCS 7 monitoring of process flows, equipment status, alarms and key process parameters.

Responsibilities
- PCS 7 supervisory-screen configuration, field commissioning, logic testing and troubleshooting.
Actions
- Prepared process-flow diagrams and integrated them into the management platform.
Outcomes
- Put wastewater and hydrometallurgy flows, alarms and key parameters into PCS 7 screens, so troubleshooting starts with the process and alarm screens instead of guesswork.